by Jean Thilmany, Associate Editor
|
communication.
The word is bandied about so frequently in management circles it's
become a buzzword. Any way you cut it, the sentiment is the same: Good
communication between management and employee fosters well-run, profitable
companies. The types of companies where managers speak openly to employees,
where manufacturing knows where mechanical engineers are coming from,
where executives tap managers' knowledge and have their fingers on the
pulse of every department.
You know, the types of places that don't exist. Or exist only in the pages
of how-to business books. How do you make that back-and-forth happen at
your company? One word, and it's a bit of a non sequitur: blueprint.
Two authors of their own business-advice book on how to carry out complex
and overarching projects say that clear, companywide communication results
from working with a good, clear plan.
"We keep track of all those books and we found one common theme: communication,"
said Vince Kasten, coauthor with Ralph Welborn of Get it Done (John
Wiley & Sons, 2006). "They tell you to communicate better, but they
don't tell you about the mechanics that need to sit behind the organization
in order to do that."
Kasten and Welborn posit that a healthy, open dialogue between company
managers and employees comes about only after higher-ups have stated a
project goal and drawn up a clear plan for how to get to the project's
end. Both authors are managing partners of global business transformation
at the information technology consulting company Unisys Corp. of Blue
Bell, Pa.
If the plan doesn't come first, managers flounder and engineering
projects go awry, they say. To blueprint, managers need intricate workings
of how projects get done. They have to know exactly how engineering works
with the manufacturing, marketing, and IT departments. Everything is interconnected,
after all.
"Let's say the CEO says, 'I want to go after the Joint
Strike Fighter contract,' " Kasten said. "What needs
to happen? You have to rapidly line up the resources of the organization
behind that goal. To do that, you need to know what connects with who,
and how and how much."
Take an example from domestic life. Say you undertake a kitchen remodel.
You can say to your spouse, "I want to remodel our kitchen for
$15,000 and have it done in time to have Thanksgiving at our place."
If that's as far as you get, the project will never be done. Best
to sit down and figure out how you'd get there. You might run cost
scenarios, shop for cabinets, figure out what you like, and compare costs.
Even more important, you'd need a timeline and a series of daily
taskslike call three contractors for comparison quotesto
get you there. You'd have to know how a contractor would work with
suppliers and subcontractors, and you'd need to know what hands-on
role you'll play.
down on paper
That concept may seem obvious. But companies often don't have blueprints
in place that they can follow to get from point A to point B. The authors
tell the story of a bank executive who boasted proudly that every project
he decreed must be done got doneon time and within budget, to
boot.
According to Kasten, "I told him, 'You're the senior
guy; people are trying to figure out how to make you happy. There could
be 200 people working behind the scenes 24/7 to support you.' "
Essentially, Kasten and Welborn advocate a kind of across-the-board method
of project management that's put in place for every project a company
takes on and is implemented across the entire organization. All departments
are connected in a predetermined way, on the blueprint. This aspect remains
much the same from project to project.
 |
| The Bell/Agusta 609 Tiltrotor,
from Bell Helicopter, takes off straight up in the air. Rotors then
tilt and the craft moves forward. Delivery is set for 2009. To keep
this huge project on track, managers follow a blueprint every step
of the way, although the plan does include some flexibility. |
"If you're running an engineering projectwhether
it's the Joint Strike Fighter or designing a new transmissionat
the end of the day you've got the same issues," Kasten said.
"People are doing their own stuff, supported by software and serving
their own goals, yet everyone has to work together and they need to know
where they're heading and how to get there, step by step.
To begin, an executive first sets a companywide goal: win the Joint Strike
Fighter contract. They meet the objective with a lot of behind-the-scenes
groundwork that executives and managers must set ahead of time and adhere
to for all projects: the blueprint. The mechanics behind the blueprint
detail how all the people and processes that make up the company will
come together to support the project.
"You can think of the company in layers: business processes, strategy,
applications, and infrastructures," Kasten said. "In each
layer, there are people highly specialized in what they do in that layer,
but they're not alone. What the mechanical engineer does for a
living depends crucially on CAD and the IT department that keeps CAD going."
Spelling out connections in such a firm way gives everyone at the company
a look at what the business does and how it does it, how to use that knowledge
to execute projects and to link from project results to business resolutions,
he added.
sail on calm waters
As project manager at BAE Systems Naval Ships in Glasgow, Scotland, Scott
Jamieson oversees the creation of two landing-ship docks for the Royal
Fleet Auxiliary. The docks are vessels that deliver the troops ashore
for an amphibious assault after marines have secured a beachhead.
Many aerospace and defense projects veer off track because managers don't
spend enough time detailing the scope of the workessentially creating
a blueprint, Jamieson said.
"The ships are complex from beginning to end," Jamieson
said. "The work we did early on was invaluable in putting us in
a position of knowledge from which we based decisions on everything from
cost and schedule to production performance."
BAE won the landing-ship dock contract in November 2001. The first vessel
was delivered to the United Kingdom's Defense Procurement Agency
late last year; the second will be delivered within the next few months.
Before engineers began work, Jamieson detailed how his group would receive
and update design drawings. The plan accounted for the 6,000 tons of steel,
the 19,000 pipes, the 8,000 meters of ventilation, and the thousands of
pieces of equipment that eventually needed to be linked.
"By investing in this plan and flushing out all of the unknowns
early on, and ensuring clear understanding of how everything related,
we had the information that we needed to make the right decisions as we
started and progressed through the phases of the build," Jamieson
said.
This plan also gave engineers and manufacturers a clear understanding
of how all the project pieces fit together and of the project's
time frame. To keep the blueprint on track, Jamieson also made sure all
groups building the vesselssuch as manufacturing and engineeringwere
in constant communication. Yes, that word again. In this case, it complemented
the blueprint.
 |
| Projects like the U.S. Joint Strike
Fighter stretch over years and include many contractors and subcontractors.
This makes preplanning vital. |
Because BAE Systems is what's termed a follow-on builderSwan
Hunter Ltd. of Newcastle-upon-Tyne, England, is building the first two
docksJamieson sometimes has difficulty getting updated design
and build information. So he ferreted out potential design and specification
changes early on.
When the design changes inevitably affect the overall plan, team members
on the engineering and manufacturing side get advance notice to better
plan for their own changes, Jamieson said.
"The plan changes, but we always know where we are against the
baseline and have a forecast of exactly where we will end up,"
he said.
Also, to help improve the return on investment, BAE
Systems recently introduced an information technology system that links
planning, finance, procurement, and production to ensure that all information
is aligned and consistent.
Although Jamieson prepared rigorously for the contract, he still reviews
his advance blueprint all the time to make sure his team uses its time
effectively. He compares that initial blueprint against the present project
to ensure that the plan is still pertinent.
"One thing we have definitely learned is that you can never know
your scope of work well enough. The work we did early on (in this area)
was invaluable in putting us in a position of knowledge from which to
base decisions on everything from cost and schedule to product performance,"
he said.
Still, Jamieson always walks a fine line between intruding upon the projectgetting
caught up in detailsand controlling the projectfocusing
solely on where it's going at the expense of where it is, he added.
out of thin air
The sky is full of examples of complex tasks. They're called aircraft.
Because aerospace projects are so large, it's easy for company
executives and managers to lose control. A blueprint helps to keep all
aspects of a huge project on track, said Jack Gallagher, executive director
for the Bell/Agusta 609 Tiltrotor.
The Tiltrotor takes off straight into the air like a helicopter. Once
in the sky, the rotors reposition, or tilt, and the aircraft moves forward.
Gallagher has worked at Bell Helicopter in Fort Worth, Texas, for more
than 36 years, many of them as a manager. "You have to take the
time to develop and to really have a good description of the task ahead
of you before you're able to analyze it and make certain decisions,"
he said.
Project risks are high in the aviation industry and because projects are
expensive, they run for a long time and have little room for error. The
BA609 project kicked off in 1991, and Bell expects to deliver the first
aircraft in about three years.
Gallagher relies on a number of software programs that grant him project
overview. He tries to assess those risks ahead of time so he can work
to mitigate them up front.
"Aeronautics is difficult because you need to act quickly and with
velocity, but you need to be patient, too, as the entire project comes
together," he said.
Gallagher is a strong proponent of working an overall plan while leaving
plenty of room to vary that plan.
A project plan, a roadmap, and a clear goal help him sidestep company
quagmires, he said.
According to Kasten and Welborn, that goes for every companyengineering
or otherwise.
"We say, if you learn how your business works and run from the
blueprintswhich really are how you do stuffyou'll
see a great improvement in how things work at your company," Kasten
said.