|
by Harry Hutchinson, Executive Editor
|
there's a
song, "Sur le Pont d'Avignon," about peoplefrom dames and
messieurs to gardeners, laundresses, and vine trimmersall dancing
on the bridge at Avignon. It's an old song with a catchy melody. It probably
refers to a one-time landmark bridge built during the 13th century on
the site of an earlier one laid down by a saint. The bridge is gone now,
but the song remains, to remind us that bridge-building goes back a long
way in France.
The old bridges have not all vanished. There are many historic structures
in daily service on French roads. They can hold up under considerable
dancing and moderate day-to-day traffic. They were never expected, though,
to bear trucks carrying machine parts that weigh almost 300 metric tons.
Few bridges of any age are ready for that.
 |
| Engineers and workers (above)
guide an extraordinary load across a bridge on the route between Port-la-Nouvelle
and Pamiers, France. Hydraulic lifts on the trailer transfer about
140 metric tons of the load through the improvised track directly
to the bridge piers. Long spans on a curve (below) proved to be a
special test for the system, which was developed by Wirzius Heavy
Assembly and Greiner Vehicle Technology. |
 |
Aubert & Duval Group, a supplier of parts, steels, and other materials
to a range of industries, had to find transport for eight machine components
of that scale. They were castings for new 40,000-ton forging presses,
which the company needed to move from a Mediterranean port to its new
factory in Pamiers.
The presses will forge fan disks for turbojet engine manufacturers, and
it is expected that some of the engines will power Europe's new
supersize jet, the Airbus A380. This operation, called Airforge, joins
another Aubert & Duval plant already operating in Pamiers.
According to Bernard Finas, project manager for what the company calls
"the Airforge 40,000-ton project," the presses have been
assembled and are due to begin operating in July.
Aubert & Duval ordered the machines from Siempelkamp Press Systems
of Germany. The forgings and castings were the work of Japan Steel Works,
which sent the finished parts to Port la Nouvelle, near Narbonne on the
Golfe du Lion on the south coast of France.
P. Wirzius Heavy Assembly GmbH of Hinden, Germany, had the job of transporting
the presses overland and assembling them at the factory in Pamiers, south
of Toulouse.
GETTING THE GREEN LIGHT
Some of those historic bridges made it impossible to take the most direct
route from the seaport to the factory, so Wirzius mapped out a route that,
although roundabout, ran on major highways. Even on the modern roads,
however, a vehicle of more than 400 tons needed special waivers from French
authorities before it could set out. Delivering the presses, though, was
considered important to the nation, so the trip received a green light.
According to Wirzius, the route was about 230 km by road. The route included
five crossings that were not up to the load of a trailer bearing one of
the huge press parts, a gross weight of 430 tons.
To find a safe way to cross its bridges, Wirzius enlisted a specialist
in getting heavy objects safely to their destinations, Greiner Vehicle
Technology, an engineering company based in Neuenstein, Germany. Greiner
says it designs systems for transporting large machinery by road or rail.
That, in fact, is what the company's bridge-crossing solution involved,
both road and rail, but not in a conventional sense.
Michael Greiner, the company's CEO, said his engineers could either
strengthen the bridges or find a way to reduce the stress on them. Rather
than trying to rebuild or shore up the structures, the company took the
second course, which is where the rail part comes in.
Working with Wirzius, the Greiner company devised a plan to transfer some
of the extraordinary vehicle weight to a temporary track system that would
channel that part of the load directly to the bridge piers.
According to the Greiner company's executives, the timeline of
their job for Wirzius meant that they needed to have as many parts of
the project as possible taking place at the same time. To make things
a little more challenging for Greiner, when it took on the job, the company
was switching its design software from a 2-D system to a 3-D product,
OneSpace Designer Modeling, from CoCreate Software in Sindelfingen, Germany.
A JUMP ON PRODUCTION
The change went well, according to Michael Greiner. "While we were
still designing, we were running the production line," he said.
"Some local suppliers were also producing individual components
even before the entire design was complete."
Given that the company had to have a workable system ready for Wirzius
in less than a calendar year, the jump on production was necessary.
According to Jochen Sailer, technical designer at Greiner, engineers working
in 3-D simulated the system in motion and avoided problems, like collisions,
that would otherwise have needed correction later.
Crews from Greiner and Wirzius tested the system at the former Butzweilerhof
Airport in Ossendorf. A transport vehicle had to transport 295 tons of
ballast across a 148-meter track. The next day, they repeated the test
as a demonstration for French motorway authorities.
 |
| A CAD rendering of the hydraulic
lift system and track design. Greiner was adopting new 3-D software,
from CoCreate, during the project. |
Transport from Port la Nouvelle to Pamiers started with two castings,
each lifted by an 800-ton hydraulic gantry onto a separate Goldhofer platform
trailer. Each trailer had 20 lines of swing axles three across and was
driven by a tractor fore and aft. Each trailer also carried a hydraulic
gantry, with two cylinders in front of the casting and two close behind.
They would be the means of transferring weight from the road to the track.
The convoy included a fleet of trucks that carried the parts of the track.
Wirzius calls it the Roll-On, Roll-Off system and holds patents for it.
The temporary track was designed to cover spans as great as 60 meters.
The first crossing had two central spans of 27.8 meters each. The track-building
team began by laying steel mats at load-bearing points on the bridge.
The rails over the mats were box girders 1.5 meters high with bolt-and-flange
couplings. This bridge needed a total of eight for each side of the trackfive
that were 10 meters long and three 8 meters long. With the help of a crane,
team members jockeyed the pieces into place.
Once the track was secure, the gantries on the trailer came into play.
They extended outward and then brought down steel wheels onto the improvised
tracks. The four hydraulic cylinders of the gantry transferred a total
of about 140 tons of the load to the track system, which channeled the
weight directly to the bridge piers. The bridge surface held the remaining
290 tons.
STAYING INSIDE THE LINES
The team disconnected the tractors and used a truck-mounted winch to haul
the trailers one at a time across the bridge at a rate of about 4 meters
a minute. Observers accompanied each trailer to make sure the wheels followed
reference lines painted on the road.
The convoy did that five times along the route, over spans of different
lengths. The span of one bridge extended almost 60 meters between supports
and lay on a curve.
The trailers progressed on the highway at speeds ranging from 15 to 30
km an hour, and stopped at points along the route, while the teams assembling
the tracks prepared crossings ahead. Delivering the castings two at a
time, the convoy made four trips in four weeks to get everything to Pamiers.
The itinerary had to be carefully plotted and the schedule kept. Traffic
was diverted from the sections of highway that the convoy was using. Bridge
sections were closed and traffic detoured for a day or more as tracks
were laid, crossed, and dismantled. Rail traffic had to be suspended to
let the convoy pass a grade crossing.
The trucks carried an identification that read "convoi exceptionnel."
The description sounds fair enough.
Each trailer was the size of a barge being pulled by one huge tractor
and pushed by another. The trailers were accompanied by a fleet of trucks,
motorcycles, and support vehicles. There were policemen, highway officials,
and a cast of engineers, technicians, drivers, and assemblers. They may
not have been exactly dancing, but they were all on the bridge together.
home
| features | breaking
news | marketplace
| departments | about
ME back issues | ASME
| site search
© 2006 by The American Society
of Mechanical Engineers
|