| This article
was prepared by staff writers in collaboration with outside contributors. |
When the Arizona Health Science Center decided
to install a power plant, it hired a San Diego contractor, Solar Turbines
Inc., to design and build a cogeneration system, a gas turbine to generate
electricity, and a heat-recovery boiler to produce steam.
Rentech Boiler Systems Inc. of Abilene, Texas, was called in to supply
the boiler. The water will be carried to the boiler by a complex system
of pipes that weave around various features of the power plant. For added
efficiency, the water will pass through a serpentine coil called the economizer,
which will make use of the boiler's own exhaust for preheating.
It was the design of the piping system that landed on the desk of Rentech's
chief engineer, Don Morran, for structural analysis.
"Before water goes into the boiler, preprocessing operations heat
the water and pressurize the piping," Morran said. "Analysis
of the piping system was required to verify its structural integrity under
pressure, temperature, and site loadings, and to ensure compliance with
the applicable ASME piping code."
The piping system started at a deaeration tank in which oxygen was removed
from the water to prolong the life of the boiler. The piping was routed
around existing features of the installation site, including platforming,
forklift trails, building barriers, and property lines.
A
PipePak model shows most of the pipeline for a cogeneration plant. Terminals
at the left enter and exit the economizer.
A control station equipped with a sensor monitored the water level inside
the boiler. The control station's valve regulated the flow of water
to keep the level consistent. Over time, due to repetitive motion, this
type of valve tends to wear out. Hence, the piping system included a bypass
around the valve so it could be replaced while the boiler was still in
operation.The economizer came farther along the line, just before it emptied
into the boiler.
According to Morran, the on-site project manager provided him with a drawing
in AutoCAD, software from Autodesk of San Rafael, Calif. Morran entered
the geometry into PipePak, which is analysis software from Algor of Pittsburgh.
Morran specified ASME B31.1-2001 as the applicable piping code by choosing
from a menu that is contained in the analysis software. Specifying the
piping code automatically set several other model parameters, including
the default load combinations.
Morran defined the piping system geometry, including pipes, bends, reducers,
valves, and other elements. He said that the model had 60 nodes, one for
each significant change along the 80.8 feet of pipeline.
Morran specified pipe data, including size, corrosion allowance, insulation,
and contents; material data, including allowable stresses from the standard
library; and load data, including temperature and pressure loads for various
operating and test conditions.
He then used the software to view the analysis results. There was a particular
span of pipe that he identified as needing more support to protect its
ends.
"In general, the end points should be as well supported as possible
because experience has shown that reducing or eliminating stresses at
the ends can prolong the life of a piping system and, more importantly,
the terminal connections," Morran said. He added supports at appropriate
locations along the line and then analyzed the revised model. Morran concluded
that stresses at the end points had been sufficiently reduced.
To verify that the piping structure complied with the ASME code, Morran
displayed the code stress ratios for each load combination, which indicated
that all stresses were safely below the allowable value. He said, "Displaying
the ratios between code stress and allowable stress is a quick and easy
way to indicate whether or not the piping system is in compliance with
code requirements. It shows immediately if there is a problem and where
it's located."
Morran used the software to automatically generate a report that summarized
input, analysis results, equipment data, and more. He said, "Probably
two hours after the job hit my desk, the report was back in the draftsman's
hands and he was drawing the additional supports that were specified as
a result of the analysis."
The power plant under construction at the center is part of the University
of Arizona in Tucson.
home |
features |
news update |
marketplace |
departments |
about ME |
back issues |
ASME |
site search
© 2002 by The American Society of Mechanical Engineers
|